StancorERP Rollout Across Four Plants
Maharashtra & Gujarat, India · Manufacturing
Overview
Enquiry-to-dispatch in one system across four plants, with heat traceability and certificates generated from the production record.
The challenge
Four plants ran on three different systems plus spreadsheets. Stock visibility was a day old at best, job costing was reconstructed monthly, and certificates were retyped from production registers.
What we did
Rollout was phased one plant and one process at a time, starting with the plant that had the cleanest master data to establish a working template. BOM cleanup consumed more effort than configuration — as it usually does. Certificates now generate from the production record, removing retyping and the errors that came with it.
Project data
| Plants live | 4 (phased over 11 months) |
|---|---|
| Stock visibility | 24 hours → real time |
| Job costing | Monthly reconstruction → per job |
| Certificate preparation | 40 min → 2 min per heat |
| Inventory carrying | -13% after planning moved to MRP |
| First go-live | 9 weeks from kickoff |
Standards applied
- ISO 27001
- GST e-invoicing (IRN)
- e-Way Bill API
Scope supplied
- StancorERP
- StancorOps